Run an EDGE quotation review that compares scope, deliverables, cost, conflicts, implementation capacity and value for money.
An EDGE quotation review should test whether a proposal is suitable and reasonably priced for the selected activity, not merely whether the total fits an expected grant percentage. Enterprise Singapore assesses support by activity, and reimbursement depends on the approved project. The applicant therefore needs a procurement decision that stands on its own commercial merits.
Make quotations comparable before choosing
Issue the same brief to credible suppliers. Ask them to separate discovery, design, configuration, equipment, licences, professional services, training, testing, travel, support and taxes where relevant. Record quantities, unit prices, assumptions, validity, payment terms, project dates and acceptance criteria. A single bundled figure prevents management from seeing exclusions and duplicated work.
Use the EDGE activity directory to identify the relevant activity and support level. The current FAQ confirms that each activity has its own requirements, costs and deliverables. A proposal should map to that activity without copying its wording or stretching a normal operating purchase into a transformation project.
Test value beyond the lowest price
Compare the proposed method, named team, relevant experience, implementation capacity, data or security controls, warranty, handover and ability to meet the business outcome. Score the material factors consistently and explain the weighting. Lowest price may be poor value if essential testing or handover is missing, while a higher price needs evidence rather than prestige.
Normalise differences before comparing totals. Remove optional items, identify internal work and calculate the same project boundary for each offer. Check related-party connections and common shareholders. Record negotiations and the final commercial reason. Do not change a supplier’s scope after seeing competitors’ confidential details without a fair process.
Keep the grant assumption outside the procurement decision
Calculate the full cash requirement, including unsupported items, GST, timing and working-capital exposure. Model support as conditional until the Letter of Offer is accepted and the claim is paid. The company must be able to fund the project without treating a forecast grant as cash already available.
Link the selected quotation to milestones and measurable acceptance evidence. If price or scope changes before approval, update the application truthfully. If it changes later, test the approved boundary and obtain any required consent before relying on it. Keep unsuccessful quotations and the decision record for audit and management review.
Turn the decision into a controlled file
Use a dated decision record that identifies the applicant, business need, current official source, chosen route, responsible owner, costs, milestones and evidence. Separate facts already verified from forecasts and assumptions. A catalogue listing, supplier statement, consultant recommendation or portal acknowledgement does not establish approval. The company remains responsible for its declarations and commercial decision.
Give each quotation, contract, invoice, payment and deliverable a stable reference. Preserve earlier versions and explain material changes instead of silently replacing them. Where the authority, tax adviser, auditor or another professional must decide a point, record the open question and obtain the required view. Do not convert uncertainty into a confident eligibility statement.
Review before commitment and again before closeout
Run four reviews: suitability, authority, implementation and closeout. At suitability, test the entity, activity and business outcome. Before commitment, freeze the proposed scope, vendor and financial assumptions. During implementation, compare actual work with approved terms. At closeout, reconcile deliverables, accepted results, invoices, full payment, operating evidence and obligations that continue.
Name the person who may approve each stage and the records that person must see. Procurement should not treat a draft application as permission to contract. A project team should not treat supplier completion as company acceptance. Finance should not treat a submitted claim as cash received. Clear status words prevent accidental commitments and weak reporting.
Handle exceptions without rewriting history
Maintain an exception log for changed facts, delayed milestones, supplier variations, cost movements, missing records and failed tests. State the effect on scope, eligibility, timing and expected value. If an authority decision or formal variation is required, use the published route before relying on the change. Silence and helpdesk receipt are not approval.
If a material defect appears, pause the affected acceptance, filing or claim item. Keep original evidence, assign corrective action and set a review date. Do not backdate records, move costs between categories or adjust a baseline after seeing the result. A candid exception with an owned resolution is more credible than a clean-looking file that cannot explain what happened.
Plan handovers before the original project team disperses. The handover should identify the current version, source locations, system access owner, next review date, open exceptions and any condition that continues after payment or filing. Restrict personal, financial and commercially sensitive records to authorised users, while giving each responsible owner enough information to perform the assigned control. Record the external event that should trigger an earlier review, such as a changed programme page, revised authority letter, supplier failure or material business change.
Verify the final outcome independently
Ask someone who did not prepare the final pack to compare the decision, current official source, approved terms, deliverables, payments and operating evidence. Recalculate totals and sample source records. The reviewer should be able to reproduce the conclusion without relying on the preparer’s memory. Record unresolved points with named owners and dates.
Use the EDGE vendor relationship guide for the wider decision and keep this article as the narrower operating guide. After submission, preserve the receipt and reconcile questions, adjustments and the final registered or paid outcome. Continue any reporting, retention, asset-use or other condition that survives closeout.
Practical review checklist
- Common brief issued
- Cost components normalised
- Supplier capability checked
- Conflicts screened
- Conditional grant assumption separated
An EDGE quotation review is complete when comparable scope, price and delivery evidence supports the commercial choice, the applicant has screened conflicts, and the project remains viable without assuming grant approval.